Proposed UK data centres could pay £100M in deposits for power demands

17 hours ago
  • Ofgem proposes refundable deposits for data centre developers to connect to the UK electricity grid, ranging from £237,500 to £712,500 per megawatt.
  • Projects seeking 1 GW of power would face upfront costs of hundreds of millions, with deposits refunded if the project is completed.
  • Electricity capacity requests have surged from 41 GW to 125 GW in the past year, exceeding the UK's 2025 peak demand of around 46 GW.
  • The proposal aims to deter speculative projects from blocking grid capacity, with key milestones required to maintain connection queue positions.
  • Data centres are controversial due to concerns over noise, electricity use, and water consumption for cooling, despite being essential for AI and digital services.