Texas halts new data centers as governor calls for audits
4 hours ago
- Texas has become a top destination for data centers due to loose regulations and abundant power, second only to Virginia.
- Governor Greg Abbott announced mandatory audits for all new data center projects by PUCT and ERCOT.
- ERCOT's interconnection queue has surged from 233 GW in January to 474 GW, with about 90% being data centers.
- Many projects are speculative; if realized, they could overwhelm the grid, representing over five times peak demand.
- Texas relies on natural gas, wind, and solar, with solar capacity quadrupling since 2021, but prices are rising.
- Data centers and crypto-mining are driving higher electricity prices, prompting Abbott to mandate detailed reporting.
- Texas historically favors light regulation, but Abbott's move to compel compliance signals a potential shift away from being a data center mecca.