Texas halts new data centers as governor calls for audits

4 hours ago
  • Texas has become a top destination for data centers due to loose regulations and abundant power, second only to Virginia.
  • Governor Greg Abbott announced mandatory audits for all new data center projects by PUCT and ERCOT.
  • ERCOT's interconnection queue has surged from 233 GW in January to 474 GW, with about 90% being data centers.
  • Many projects are speculative; if realized, they could overwhelm the grid, representing over five times peak demand.
  • Texas relies on natural gas, wind, and solar, with solar capacity quadrupling since 2021, but prices are rising.
  • Data centers and crypto-mining are driving higher electricity prices, prompting Abbott to mandate detailed reporting.
  • Texas historically favors light regulation, but Abbott's move to compel compliance signals a potential shift away from being a data center mecca.